Description
Brownfield Pre-Polymer Facility adjacent to existing operating plant

Scope of Work
• Front-end load based on similar facility at Paulsboro, NJ; +/-10% TIC
• Design and specify over 200 pieces of equipment and 1000 instrument devices
• 3D model with over 600 lines (pipe stress analysis on required lines)
• Approximately 700 tons of steel and 2500 cubic yards of concrete
• Hot oil jacketed piping and tankage
• Lump sum basic engineering and lump sum detailed design
Challenges
• New client with close ties to home office in Europe
• Limited owner support staff
• Large vendor modules incorporated in layout
• New Jersey permit process
• Owner controlled interfaces; coordination critical
Keys to Success
• Lines of communication
• Establish trust and confidence