Description

• New industrial nylon yarn facility for tire core.

• Facility part of a vertically integrated tire production complex.



Scope of Work

• Engineering, design and project controls for new nylon facility

• On-Board provided mechanical, process, electrical, instrumentation, civil, structural and architectural design for the project

• 3D design utilizing PDMS


Challenges

• Multicultural project team

• Inflation

• Earthquake


Keys to Success

• Integrated project team

• 3D design

• Seismic design